24-hour TSP Monitoring Results                            
                                     
Station AM7 (Rooftop of West Kowloon No.2 Sewage Pumping Station)                    
Start Finish Weather Filter Weight (g) Elapsed Time Reading Sampling Time Flow Rate (m3/min) TSP Conc. Action Level Limit Level Observations / Remarks Sampler Filter
Date Time Date Time   Initial Final Initial Final (hrs) Initial Final Average  (µg/m3)  (µg/m3)  (µg/m3)   ID ID
03-Nov-11 16:00 04-Nov-11 16:00 Sunny 2.8045 2.9000 9406.84 9430.84 24.00 1.3470 1.3470 1.3470 49 207 260 Dust from Project site, traffic emission and  dust from other construction sites A.001.12T 13691
09-Nov-11 16:00 10-Nov-11 16:00 Fine 2.7818 2.8276 9430.84 9454.84 24.00 1.3470 1.3470 1.3470 24 207 260 Dust from Project site, traffic emission and  dust from other construction sites A.001.12T 13717
15-Nov-11 16:00 16-Nov-11 16:00 Fine 2.7922 2.9731 9454.84 9478.84 24.00 1.3370 1.3370 1.3370 94 207 260 Dust from Project site, traffic emission and  dust from other construction sites A.001.12T 13749
21-Nov-11 16:00 22-Nov-11 16:00 Fine 2.8015 2.9555 9478.84 9502.84 24.00 1.3370 1.3370 1.3370 80 207 260 Dust from Project site, traffic emission and  dust from other construction sites A.001.12T 13791
27-Nov-11 16:00 28-Nov-11 16:00 Sunny 2.8065 2.9171 9502.84 9526.84 24.00 1.3470 1.3470 1.3470 57 207 260 Dust from Project site, traffic emission and  dust from other construction sites A.001.12T 13782
                        Min. 24          
                        Max. 94          
                        Average 61